Renovation Updates
Updated 10/3/2024
Renovation Update
Interior:
The choir loft is really taking shape! Our carpenters have been hard at work framing it, and it’s starting to look like a beautiful addition to the church.
Electricians have been setting up all the behind-the-scenes wiring to make sure everything is ready for the new space.
We’ve also been opening up some walls, clearing out old areas to make way for improvements in the Narthex.
Electricians have been setting up all the behind-the-scenes wiring to make sure everything is ready for the new space.
We’ve also been opening up some walls, clearing out old areas to make way for improvements in the Narthex.
Exterior:
Our team poured new foundation walls and worked on the lower-level elevator wall. The pretty stuff is coming soon!
Fellowship Hall Routine During Renovation
To enable Paric and CLC to most effectively share the Fellowship Hall throughout the construction period, Paric is taking responsibility for the round tables, and we are responsible for the chairs. If they have taken the tables down during the week, they will set them back up before leaving on Friday. And we will make sure the chairs are re-stacked and out of their way after we use them on Sundays.
Here’s how you can help: If you arrive at Adult Forum before church or Fellowship after church and find that additional chairs are needed at the tables, please help set a few more out. And as you leave Fellowship, please help re-stack a few chairs over by the kitchen pass-through. This is definitely one of those tasks that goes much quicker with several people involved. THANK YOU!!